Construction Updates - March 2011


With already over 30% lots sold in Phase 2, lot clearing works are complete and all planned road networks are totally grubbed and cleared.

In Phase I facing the sea, where 60% of lots are sold, on the Hotel’s right side, Section A (Lots 33, 35, 37 and 39) road completion is complete and is at 98% completion with water line fittings and street lights nearing installation.

Road completion on the opposite side, to the left side of the Hotel, SECTION B (area of Lots 20 to 30) works are coming along with finishing works for sidewalk works at 96%, while Section C for Lots 1 through 18 is also now at 96%.

Phase 1 is due to reach 100% completion by April 2011.